November 22, 2024
Construction activity: CUPx construction trailer and utility install
(SACRAMENTO)
The mobilization of the Central Utility Plant expansion (CUPx) construction trailer and underground utility installation will begin Tuesday, Nov. 26.
Please note the following details of this activity:
-
The UC Davis Health Institute for Regenerative Cures parking lot 30 will be impacted (see below).
-
Traffic control will be in place during construction to minimize impacts on traffic flow and parking.
-
Work will be completed in phases to keep as much parking available as possible.
-
The first phase will wrap up mid-December.
-
All work connected to the construction of the trailer is slated to wrap up March 2025.
For further assistance, please contact Jake Bertacchi at j.bertacchi@ccm.to or Wes Ramirez at wesramirez@ucdavis.edu.